Currently, the Thai-Chinese high-speed railway system (Phase 1: Bangkok–Nakhon Ratchasima Section) is under construction. Of the total 14 civil work contracts, construction is ongoing under 10 contracts and is being prepared for the remaining four contracts. With respect to the railway system and procurement of rolling stocks which are under one contract, work is in the designing process.

Contract 2-3
Railway System, Mechanical and Electrical Systems, Procurement of Rolling Stocks, and Personnel Training

Length :

Contractor : China Railway International Company Limited and China Railway Design Corporation (a Chinese state enterprise)

Progress

Scope or work:

- Railway system

- High-speed train system (e.g. electrical system, signaling system, communications system)

- Procurement and supply of rolling stocks

- Personnel training (for train operation and maintenance)

- Technology transfer

 

Contract signing: 28 October 2020

 

NTP for design: 22 December 2020